1. Before starting the equipment, a careful inspection must be carried out to check for any obstacles near the conveyor line, especially to check if the operating components are intact: chain plates, pin shafts, and shaft sleeves are not broken or damaged, material grooves are not deformed or cracked, rollers are not severely damaged or cracked, bolts are not loose or lost. If the inspection is qualified, contact the equipment operators who are connected to the front and back of the equipment can be made, Once everything is ready, we can start.
2. Driving sequence:
a. Ring alarm: to allow people near the device to leave.
b. Start the relevant receiving equipment or other devices (such as connected dust collectors).
c. Start this conveyor.
d. Start the feeding equipment.
3. Parking
a. Notify the upstream equipment of the conveyor to stop feeding.
b. Unload all materials from the conveyor chute.
c. Parking.